Updated Road Program Schedule!

From
Wrightstown Township

Wrightstown Township Logo

Sent
Fri, Jul 24 @ 9am

Where
View on Map

Description
Below is the updated schedule (07/23/2026) weather dependent:
Haines Paving & Landscaping Inc. is the contractor responsible for the road repair contract and then AMS will be the contractor responsible for the oil and chip and slurry seal.

•Monday July 27th-Friday, July 31st- Mud Road Crossover Pipe- It will take up to 4 days, and the road will be closed from 7AM-7PM during work (local access will be maintained). Mud Road will be closed from Penns Park Road up to 560 Mud Road. Anyone who needs to access 560 Mud Road or beyond that point should access Mud Road from Worthington Mill Road.

•Monday, August 3rd Hallowell, Wooley and Crescent Drive Mill and Paving is tentatively scheduled but depends on the completion of the projects above. No parking will be allowed on the roadway during this time- homeowners will be notified once the date is set.

•Tuesday, August 4th (weather dependent) Oil and Chip will take place on the following roadways and Slurry Seal is scheduled to be applied on Monday, August 10th (AMS should be dropping off notifications to residents ahead of this to help explain the process):
o Thompson Mill Road- Oil and Chip
o Mud Road- Oil and Chip
o Fox Hill Drive- Oil and Chip/Slurry Seal
o Martindell Drive- Oil and Chip/Slurry Seal

For more information, please visit https://www.wrightstownpa.org/resources/news/article/?id=6310