PennDOT performing work on Route 30

From
Hellam Township

Hellam Township Logo

Sent
Fri, Sep 12 @ 9am

Where
View on Map

Description
Message from PennDOT:

September 10, 2025

Resurfacing Project Begins on Route 30 in York County

Harrisburg, PA – The Pennsylvania Department of Transportation (PennDOT) announced today that a resurfacing project has begun on Route 30 in York County.

This project consists of milling, asphalt resurfacing, base repair, concrete paving, concrete patching, drainage improvements, guiderail updates, line painting, sign updates, structure repairs and other miscellaneous construction on Route 30 (Arsenal Road) from just west of the Route 462/Hallam Exit to the Wrights Ferry Bridge spanning the Susquehanna River.

Drainage work began this week along the shoulder of eastbound Route 30. This work is being performed at various locations off the roadway and no impacts to traffic are expected.

Structure repairs are expected to begin at Cool Springs Road bridge spanning Route 30 on Monday, September 22. There will be shoulder closures on eastbound and westbound Route 30, weather permitting.

Reconstruction of the westbound off-ramp at the Route 462 (Hallam) Exit is scheduled from Sunday, October 5, to Sunday, October 12, weather permitting. This work will require the ramp to be closed and traffic to be detoured. An updated press release will be issued prior to this work.

Milling and paving on eastbound and west bound Route 30 will take place during the 2026 construction season.

New Enterprise Stone and Lime Company, Inc., of New Enterprise, PA, is the contractor on this $15,475,000 project.

All work on this contract is expected to be completed by December 21, 2027.

Attachments

This notification was posted by Hellam Township. Hellam Township is solely responsible for this notification and unless specifically indicated, no other community or individual utilizing Savvy Citizen is sponsoring, responsible for, or endorsing this notification.

Back to Hellam Township's Calendar