Bolton Bridge Updates

From
Borough of Abbottstown

Borough of Abbottstown Logo

Sent
Fri, Jun 6 @ 4:49pm

Where
View on Map

Description
SCHEDULE MILESTONES
• The Notice to Proceed for WO1 – Preliminary Design was executed 6/5/2024
• Amendment 1 executed 9/16/24
• Amendment 2, No cost transfer, submitted 6/4/25. NTP Pending.
• Current District Let Date: 4/1/2027 (tentative)
• Environmental Clearance: 7/15/25 (may push in August/September)
• Design Field View: 7/17/25 (may push in August/September)
• ROW Plan Approval: 11/26/25
• Utility Clearance: 7/17/26
• Permit Approval: 8/4/26
• PS&E: 9/16/26

APPROVALS AND/OR ACTIVITIES COMPLETED SINCE LAST REPORT
• Pre-TS&L Concurrence received 6/2/25
SUBMISSIONS CURRENTLY UNDER REVIEW
• Updated scoping document ready for District review in CEES
• Revised wetland report

ACTIVITIES SCHEDULED FOR NEXT 2 MONTHS
• Finalize TS&L and H&H and SEPS (early July submission)
• Perform Phase II archaeology field work (mid-June)
• Prepare Public Involvement Plans
• Begin CE document after scoping approval.
• Progress E&S plans and ROW plans
• Enter preliminary utility conflicts into URMS

ANTICIPATED SUBMISSIONS/APPROVALS IN THE NEXT 2 MONTHS
• E&E Scoping approval
• Preliminary results of archaeology phase II work (late June)
• Submit TS&L, H&H, SEPS (late June/early July)
• Submit Public Involvement Documents to District/CO.
• Updated costs to District by 6/23/25.

UNRESOLVED PROJECT ISSUES REQUIRING RESOLUTION OR INFORMATION
• None

This notification was posted by Borough of Abbottstown. Borough of Abbottstown is solely responsible for this notification and unless specifically indicated, no other community or individual utilizing Savvy Citizen is sponsoring, responsible for, or endorsing this notification.