    SCHEDULE MILESTONES
• The Notice to Proceed for WO1 – Preliminary Design was executed 6/5/2024 
• Amendment 1 executed 9/16/24 
• Amendment 2, No cost transfer, submitted 6/4/25. NTP Pending. 
• Current District Let Date: 4/1/2027 (tentative) 
• Environmental Clearance: 7/15/25 (may push in August/September)
• Design Field View: 7/17/25 (may push in August/September)
• ROW Plan Approval: 11/26/25 
• Utility Clearance: 7/17/26 
• Permit Approval: 8/4/26 
• PS&E: 9/16/26 
APPROVALS AND/OR ACTIVITIES COMPLETED SINCE LAST REPORT 
• Pre-TS&L Concurrence received 6/2/25 
SUBMISSIONS CURRENTLY UNDER REVIEW 
• Updated scoping document ready for District review in CEES 
• Revised wetland report 
ACTIVITIES SCHEDULED FOR NEXT 2 MONTHS
• Finalize TS&L and H&H and SEPS (early July submission) 
• Perform Phase II archaeology field work (mid-June)
• Prepare Public Involvement Plans 
• Begin CE document after scoping approval. 
• Progress E&S plans and ROW plans 
• Enter preliminary utility conflicts into URMS 
ANTICIPATED SUBMISSIONS/APPROVALS IN THE NEXT 2 MONTHS
• E&E Scoping approval 
• Preliminary results of archaeology phase II work (late June) 
• Submit TS&L, H&H, SEPS (late June/early July) 
• Submit Public Involvement Documents to District/CO. 
• Updated costs to District by 6/23/25. 
UNRESOLVED PROJECT ISSUES REQUIRING RESOLUTION OR INFORMATION
• None