INGRAM AVENUE PROJECT

From
Ingram

Ingram Logo

Sent
Tue, Oct 13 @ 3:22pm

Description
🚧 Key Project Locations for Wednesday 10/14/2026

• Manhole Casting Replacements: Work is to be concentrated to Ingram Avenue between Schley Avenue and Sampson Avenue and the Wynne Avenue & Ingram Avenue intersection.

• Excavation Work: Heavy digging and excavation are focused at the intersection of Admiral Dewey and Ingram Avenue.

This schedule is weather dependent and subject to change.

🚗 Traffic Impacts & Transit Details

• Alternating Single-Lane Traffic: Ingram Ave. will be open to traffic utilizing flaggers and single lane alternating traffic.

• Limited Side-Street Access: Ingress and egress (entering and exiting) to the various side streets connecting to Ingram Avenue will be limited at periodic intervals.

• School Commutes unaffected: The borough has verified with the Montour School District that all student bus routes and timing will remain exactly the same.

Paving Notices were handed out by the Road Contractor today to the resident’s being directly affected.

Thank you.

This notification was posted by Ingram. Ingram is solely responsible for this notification and unless specifically indicated, no other community or individual utilizing Savvy Citizen is sponsoring, responsible for, or endorsing this notification.