Construction Project Update - August 2026

From
Forest Hills

Forest Hills Logo

Sent
Mon, Aug 24 @ 10:56am

Description
2026 ROAD PROGRAM -

Final wearing course (or top layer of paving) has been applied. Adjustments as determined through final inspections will take place in the coming months. Soft surface restoration will be scheduled accordingly.

COMPREHENSIVE RECONSTRUCTION: AVENUE D -

There will be a 2 - 3 week break on this project due to a delay in materials. The project is slated to pick back up in early September and last throughout the month. Updates will be provided as more definitive dates are in place.

Cold patch asphalt repair at the intersections of Avenues F and D is slated for this week.

PEOPLES GAS MAINLINE RENEWAL -

Roberta Drive Area Project:

Milling and paving is slated to occur starting September 14th. Soft surface/yard restoration will occur after milling and paving is completed or at a time that is appropriate for successful restoration results. Roads affected:

Roberta Drive
Williams Place
Ridge Avenue
Maine Street
Geisler Drive
Parise Road

Burlington Road Area Project:

Active construction will continue through September on the following roads. Road reconstruction will occur later in the year.

Burlington Road
Norway Road
Batavia Road
Edgewood Road
Bevington Road

Updates will continue to be distributed through Savvy Citizen and will be available on our website on the Plans and Projects page: https://www.foresthillspa.gov/ongoing_and_planned_projects.php




This notification was posted by Forest Hills. Forest Hills is solely responsible for this notification and unless specifically indicated, no other community or individual utilizing Savvy Citizen is sponsoring, responsible for, or endorsing this notification.

Back to Forest Hills's Calendar