2026 Road Paving Project - update

From
Forks Township

Forks Township Logo

Sent
Thu, Aug 20 @ 8:51am

Where
View on Map

Description
The 2026 road paving project began on Monday, August 17, 2026. New Enterprise is the company who has been awarded the contract.

The following streets will be milled and paved – Blossom Hill Road, Clarendon Drive, Roseberry Avenue and Ramblewood Drive.

The milling process was delayed which delayed the paving.

Paving is the next step which will occur on Friday, August 21st and Monday, August 24th.
Attached is a map of the paving schedule. Residents are asked to please park on an adjacent street the day your street is paved.

Day 1 – Clarendon, a portion of Ramblewood, Roseberry. (now Friday, August 21st)
Day 2 – Blossom Hill, Ramblewood (now Monday August 24th)

We apologize for the inconvenience.

Attachments

This notification was posted by Forks Township. Forks Township is solely responsible for this notification and unless specifically indicated, no other community or individual utilizing Savvy Citizen is sponsoring, responsible for, or endorsing this notification.

Back to Forks Township's Calendar