2026 Road Paving Project - update
From
Forks Township
Sent
Thu, Aug 20 @ 8:51am
Where
View on Map
Description
The 2026 road paving project began on Monday, August 17, 2026. New Enterprise is the company who has been awarded the contract.
The following streets will be milled and paved – Blossom Hill Road, Clarendon Drive, Roseberry Avenue and Ramblewood Drive.
The milling process was delayed which delayed the paving.
Paving is the next step which will occur on Friday, August 21st and Monday, August 24th.
Attached is a map of the paving schedule. Residents are asked to please park on an adjacent street the day your street is paved.
Day 1 – Clarendon, a portion of Ramblewood, Roseberry. (now Friday, August 21st)
Day 2 – Blossom Hill, Ramblewood (now Monday August 24th)
We apologize for the inconvenience.