Valley Vista Drive Improvement Project Update

From
Patton Township

Patton Township Logo

Sent
Thu, Jul 16 @ 9:53am

Description
The following updated schedule has been released as of Thursday, July 16th.

All work will be performed from 8 pm-6am.

7/16 – Thursday Night to Friday morning – Scratch left lane - Sewer work would be able to be performed Friday during the day.
7/20 – Monday night to Tuesday morning – Overlay right lane. Monday during the day the sewer company could continue their work if necessary.
7/21 – Tuesday night to Wednesday morning – Overlay left lane.
7/22 – Wednesday night to Thursday morning – Finish up overlay if necessary.

Thank you for your patience as this project is wrapped up!