on May 11 and continue until May 15 on the following roads:

5/11/26 – Starting at 7 AM, milling Drummer Drive, then moving to mill the shoulder of Brickyard Road
5/12/26 – Starting at 7 AM, paving Drummer Drive
5/13/26 – Starting at 7 AM, paving Brickyard Road
5/14/26 – Starting at 7 AM, paving Brickyard Road; potential line striping late
5/15/26 – Line striping in the morning