2025 Local Road Paving Program

From
Upper Chichester Township

Upper Chichester Township Logo

Sent
Thu, Oct 30 @ 3:16pm

Description
The 2025 Upper Chichester Township local road repaving program will be taking place between Friday, October 31, 2025 and Thursday, November 13, 2025. Work will take place during regular business hours Monday - Friday excluding holidays; schedule subject to change based on weather conditions.

This year, contractor Allan Myers, LP will be completing a $436,077.40 project with the majority of the funding coming from the Pennsylvania Liquid Fuels Fund.

If your street is in the list below you will receive a door hanger advising you of the dates your street is scheduled for work. On days while work is active, please remove all vehicles from the street by 6:30 a.m.

Residents will be able to access their homes, but traffic may be restricted and street parking will be prohibited until the work is completed. Please do not drive through barricades, as these are placed for the safety and protection of the workers.
Unless absolutely necessary, please do not drive or walk across freshly tarred or paved street. The oils and tar will stain cars, clothes, carpet, etc.

Thank you in advance for your cooperation.

Tentative Day 1: 10/31/2025 - Road Milling
- Arrowhead: Boxwood to Cherry Tree
- Orchard Way: Cherry Tree to Springton
- Sommerset: Chatham to 4337 Sommerset
- Broadway: Williams to End

Tentative Day 2: 11/3/2025 - Road Milling
-Friends Way: Meetinghouse to Ferncroft
-Malatesta: Blueball to End
-Ryan's Run: Bethel Line to near Rockford
-Yorktown Drive: Larkin to Revolution

Tentative Day 3: 11/5/2025 - Road Milling
- Kelly Avenue: Larkin to End
- Phillip Drive: Whitney to Eric
- Whitney Avenue: Phillip to End

Tentative Day 4: 11/6/2025 - Road Paving
- Whitney Avenue: Phillip to End
- Phillip Drive: Whitney to Eric
- Kelly Avenue: Larkin to End

Tentative Day 5: 11/7/2025 - Road Paving
- Yorktown Drive: Larkin to Revolution
- Ryans Run: Bethel Line to near Rockford
- Malatesta: Blueball to End
- Friends Way: Meetinghouse to Ferncroft

Tentative Day 6: 11/10/2025 - Road Paving
- Broadway: Williams to End
- Sommerset: Chatham to 4337 Sommerset
- Orchard: Cherry Tree to Springton
- Arrowhead: Boxwood to Cherry Tree

Tentative Day 7: 11/12/2025 - Road Milling
- Creek Parkway: Seem halfway to SR 322 to Furey Road

Tentative Day 8: 11/13/2025 - Road Paving
- Creek Parkway: Seem halfway to SR 322 to Furey Road

Attachments