Warren Street Construction - Week Ending October 31st
From
Borough of Crafton
Sent
Fri, Oct 24 @ 3:22pm
Description
Warren Street Construction - Week Ending October 31st
🚧 NOTICE: Broadhead Sewer Separation Project – Warren Street/Crafton Boulevard 🚧
â›” No daytime parking on BOTH SIDES of Warren Street from Broadhead Avenue to N. Linwood - Do not park after 7:00 am on workdays
During the week ending October 31 - Construction on the Warren Street portion of the Broadhead Sewer Separation Project will continue. One crew will be beginning concrete work Monday at the bottom by Broadhead Avenue, while the sewer crew will be installing pipe up the street. This work includes complete road reconstruction with new curbs and asphalt pavement.
Because of this construction, residents will not be able to park on BOTH SIDES of Warren Street from Broadhead Avenue to N. Linwood Avenue. Please do not park in this area after 7:00 am on workdays to prevent project delays and possible fines. Parking and street access will be available after work hours.
â›” 2500 Crafton Blvd Residents will have limited access to the parking lot by the end of the week; the contractor will work with residents to help them access their cars and available parking.
Check here for updates: https://www.craftonborough.gov/constructionprojects
Future impacted streets include:
Crafton Blvd (between the Trail entrance and Broadhead Ave.)
Broadhead Avenue
Parke Street
Coulter Street
Crennel Avenue
N. Linwood Avenue
N. Emily Street
Belvidere Street
We appreciate your patience and understanding as we work to improve the infrastructure in our neighborhood.