Crafton Borough - Night Work Construction

🚧 NOTICE: Night Work Scheduled – Water Line Relocation 🚧

Attention residents: Starting Monday, August 18th, Wilson Excavating will be working overnight to relocate PA American water lines at the W. Crafton / Steuben intersection. This work is supplementary to the ongoing Steuben, Duncan and Linden Sewer Separation Project and is expected to last for approximately one week.

🔹 Work Hours: Nighttime (7PM to 5AM)
🔹 Expected Duration: 1 week max
🔹 Purpose: Water line relocation to accommodate new storm sewer
🔹 What to Expect: Noise, lights, and possible traffic detours in the work zone

We appreciate your patience and understanding as we work to improve the infrastructure in our neighborhood.
The Borough remains under the impression that night work is no longer expected for the actual sewer construction.