2024 Road Paving Notice
From
Borough of Crafton
Sent
Sun, Sep 15 @ 9am
Description
Crafton Borough has been notified by the paving contractor, Folino Construction, that the 2024 Road Paving Program work will begin this week.
The current paving schedule for this week provided by Folino is as follows:
• Milling Monday and Tuesday
• Reinstalling guiderail on Promenade Monday or Tuesday before paving starts
• Paving binder course on Wednesday and Thursday
• Paving wearing course on Friday and Monday
Plan is subject to change due to weather and/or other discovery which need to be repaired.
The paving street list again is below:
• Orchard Street – From S. Linwood to S. Grandview intersections
• South Grandview Avenue – From Ewing Road to Woodlawn intersection
• Locust Street – All of Locust Street
• Manor Street – All of Manor Street between Kingston and Hawthorne
• McMunn Avenue – From 97 McMunn to 199 McMunn
• Promenade Street – From Chartiers to High Street intersection
• Middle Street – All of middle Street
• South Linwood Avenue – From Promenade to Woodlawn intersection
Please see the attached maps for reference of what streets will be impacted by this road work.
Thank you!
Borough of Crafton