Road Construction projects
From
Caernarvon Township (Berks)
Sent
Thu, Aug 1 @ 4:09pm
Description
Mountaineer Village Project
This project is scheduled to start on Monday August 5
The project has several steps before. Completion
1) Reclamation of the existing road surface
2) Add a cement based stabilizer
3) Perform a grading operation followed by compaction
4) After a 14 day curing period and proof testing crews will return add the final paved road surface
Please contact the Township Office with concerns .
Temporary road closures and delays should be expected.