The Contractor will begin the milling of the roadways August 22. The schedule of roads to be milled are as follows:

1. SERVICE ROAD NO. 3
2. MARION AVENUE
3. FILMORE ROAD
4. CASCADE ROAD
5. ROXBURY ROAD
6. HAWTHORNE ROAD

The Contractor will begin the paving next Tuesday, August 29. The roads will be paved in the same order as they will be milled. The paving for each road is anticipated to occur 1 week after each respective road is milled.