2023 Project Schedule
From
Edinboro
Sent
Fri, Mar 31 @ 2:18pm
Description
The following projects will occur this summer in the Borough of Edinboro. Dates are tentative, and some projects are weather-dependent. Please share with your neighbors!
US-6N / PA-99 & 6N / Ontario St Intersections
(June through September)
Delays and detours for 6N/99 & 6N/Ontario; Intersections will be widened and lanes re-aligned; Includes paving 6N between 99 & Ontario and new crosswalks and lighting
Rt. 99 Sidewalk
(May through August)
New sidewalk north along Rt. 99
Annual Paving
(June through August)
Beau from Casey to Sherrod Hill
Casey from Sherrod Hill to Beau
Sherrod Hill from Chestnut to End of Borough
Lakeland from Evergreen to Dundon
Lynwood from Lakeland to Hillcrest
Sherwood from Lakeland to Hillcrest
Harrison Drive Water Line
(July through August)
Year 1 of 2 replacing water line on Harrison Drive
Water/Sherrod Hill Storm Sewer
(May through June)
Storm sewer line repairs on Water St. & Sherrod Hill
Nature’s Outlet Improvements
(August through September)
Year 1 of 2 for improvements to Nature’s Outlet Park: includes installation of sidewalk, lighting, railing along the water, and accessible picnic tables
Wastewater Dept.
(Throughout the year)
Various sewer line and manhole work in the following areas: Lakeside, Shelhamer, Nordmere, Scots Glen, Stonehaven, Normal, Raspberry, & Ontario