2022 Paving Program Update
From
Forks Township
Sent
Wed, Aug 24 @ 3:26pm
Description
The contractor is ahead of schedule and plan to perform the following work as per schedule below:
Thursday August 24, 2022
Final Asphalt Coat - Nelson, Johnson, Myrtle, Cottage
Milling - Treeline Drive (Meadow Lane to Ramblewood)
Milling - Peach Tree Trail (Toboggan Trail to Dead End)
Friday August 25, 2022
Final Asphalt Coat- Treeline Drive (Meadow Lane to Ramblewood)
Final Asphalt Coat - Peach Tree Trail ( Toboggan Trail to Dead End)
Schedule is subject to change based on weather, equipment breakdowns and asphalt plant issues.
We appreciate your patience during the paving process