Road Construction Schedule Week of June 8

From Clayton
When Mon, Jun 8, 2020 @ 7am to Fri, Jun 12, 2020 @ 5pm

For the week of June 8th the following work items are planned:
1. Fine grade gravel in preparation for paving along James Street and Riverside Drive (James Street from Huginin to Riverside Drive and Riverside Drive from James Street to John Street)
2. Place asphalt pavement along James Street and Riverside Drive (between Hugunin Street and John Street)
3. Continue to set drainage structures tops to final grade along Riverside Drive
4. Continue rock removal for storm drainage and conduit duct bank installations along Riverside Drive
5. Continue installation of storm drainage system along Riverside Drive (between Merrick Street and Webb Street)
6. Continue installation of buried utility conduit duct banks along Riverside Drive (between John Street and Webb Street)