Road Construction Schedule Week of June 1

From Clayton
When Mon, Jun 1, 2020 @ 7am to Fri, Jun 5, 2020 @ 5pm
Where
View on Map

For the week of June 1st the following work items are planned:
1. Install utility vault risers and lids along James Street and Riverside Drive (between Hugunin Street and John Street)
2. Install new curbing along James Street and Riverside Drive (between Hugunin Street and John Street)
3. Continue installation of lighting conduits and light pole foundations along James Street and Riverside Drive
4. Continue installation of storm drainage system along Riverside Drive (between Merrick Street and Webb Street)
5. Continue installation of buried utility conduit duct banks along Riverside Drive (between John Street and Webb Street)

This event was posted by Clayton. Clayton is solely responsible for this event and unless specifically indicated, no other community or individual utilizing Savvy Citizen is sponsoring, responsible for, or endorsing this event.